Cedar Park Road Construction Update May 2006

Cedar Park Road Construction Update May 2006

Attention: open in a new window. PDFPrintE-mail

New Hope Drive

  • Widen to four-lane roadway with center turn lane, raised medians at major intersections and sidewalks.
  • Expected completion October 2007.

RM 1431/US 183 – Intersection

  • Jointly funded between city and TxDOT.Map of Cedar Park Road Construction Update
  • Six-lane intersection with addition of dual left turn lanes and free right turn lanes at each leg of intersection.
  • Expected completion April 2006.

Anderson Mill Road South

  • Construction of 2300 linear ft of a four-lane divided roadway.
  • South end connects to new section that follows current FM 2769.
  • Realignment of FM 2769 to form a T-intersection with proposed Anderson Mill Rd.
  • Open to public in October 2006.

Park Street/ US 183 - Intersection

  • Installation of turn lanes on Park Street at intersection with US 183.

East Park Street Extension

  • Completed in April 2006.

El Salido Parkway

  • Two-lane roadway with curb and gutter, buried storm sewer system and wide outside shoulders for bike traffic.
  • Expected to begin in August 2006 and complete by January 2007.

East Little Elm Trail – Kent Street Realignment

  • Realignment and reconstruction of East Little Elm Trail at the intersection of US 183 to increase mobility and safety at the intersection.